Despite Punjab’s opposition, the federal government has finally approved the desperately needed Karachi Circular Railway that will cut travel time by half for the city.
It will take four years to build, cost Rs246.6 billion and the Japanese are paying for 94% of it in the form of a long-term loan.
The big decision was made on Thursday by the Executive Committee of National Economic Council (ECNEC), the highest authority to approve development projects. It is headed by Finance Minister Dr Abdul Hafeez Shaikh.
A mega scheme of such nature is expected to help reduce traffic on congested roads.
The project has been delayed over design and funding snags and faced resistance from the transport lobby in the largest city of the country. As time slipped by, the cost quietly doubled.
Punjab’s opposition came out of the blue. The most populous federating unit opposed the project on the grounds it would consume a major chunk of federal resources, depriving the other provinces of their share. To pacify the Punjab, the committee has decided to keep the Karachi Circular Railway outside the Public Sector Development Programme, according to an official of the Planning Commission.
The public sector development programme tackles infrastructure that is fully or in some cases largely funded by the federal government out of its own resources. The 2012-13 programme has 1,084 schemes and a budget of Rs360 billion. Their total cost, however, is roughly Rs1.9 trillion.
The Planning Commission official said that Punjab was of the view that if a major chunk of the money was set aside for only one scheme so that it went ahead quickly, work would be delayed on other equally important projects. However, this argument perhaps holds little water as the Japanese are paying for the KCR. The remaining bill will be footed by Pakistan.
Lahore is going ahead with its own mass transit project, the Rs1.54 billion, 7.3 kilometre Ferozepur Road bus rapid transit project. Karachi is also about to start construction on a dedicated bus lane – a 22.4-kilometre track from Dawood Chowrangi in Landhi to Numaish Chowrangi in Saddar.
The BRT will be an addition to the KCR. JICA will revive the existing Karachi Circular Railway by proposing a dualisation of the 29km long track, according to the finance ministry. ECNEC asked the government of Sindh to work with the ministry of railways.
However, the fluctuation in the exchange rate is expected to increase the cost in the coming years, said the Planning Commission official. The good news is that JICA’s loan comes at comparatively cheaper rates.
Under the project, a 44km-long dedicated dual track would be laid and 24 stations would be built. The system is designed for 100 kilometers per hour speed and electric trains would operate at an approximate speed of roughly 40km per hour. This would allow it to go around the loop in around an hour.
Out of its route, over 22km would be elevated and four kilometers would be in tunnels, while the remaining around 16km would be on the road’s surface.
Against these developments, a Muttahida Qaumi Movement delegation met Prime Minister Raja Pervez Ashraf, seeking fresh assurances that Karachi’s infrastructure works would be wrapped up in time. On their list was the Lyari Express Way, Karachi Circular Railway, Karachi-Hyderabad Motorway and Karachi water supply project. Dr Farooq Sattar’s invitation to inaugurate the Lyari Express Way in September this year was accepted by the PM.
Published in The Express Tribune, August 17th, 2012.
COMMENTS (12)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ
@Mohd Butt: Karachi City generates enough revenue to pay for such infrastructure projects. Revive the city govt and let its have its own budget generated by its own revenue sources the way Musharraf did, and you won't have to worry about Punjab footing the bill. Also note that KCR operated successfully in Karachi till 80s till the transport mafia from north of the country came in and deliberately created a situation that destroyed it.
@S. Ali Raza: Who is going to pay back this loan? Sindh governament or Karachi administration ? Federal governament out of resources which are supposed to be distributed as per agreed share. Stealing of electricity is not enough, now stealing the share of future revenue also? Shame is not enough for this action.
Many influential people will fill their pockets in the name of payment to settlers on Railways land and elsewhere.
Petty thinking & approach of Punjab government! Very disappointed with Punjab government.
This is a great project however, at this time it is just an election stunt. Government won't be able to finish even the feasibility report before elections.
@S. Ali Raza:
Here we go again. Punjab can be abused and split into pieces and everyone is happy. But when it comes to Punjab's concerns, even expression of those concerns becomes blasphemy.
What? why was Punjab opposing it, when 94% was Japanese investment to begin with? Why can't they see Karachi's infrastructure or situation improve. Is it because Lahore appears better developed and peaceful in comparison then?
I don't trust such news, i have being hearing this since late 2006 that karachi will be getting a circular railway, back then i was happy that i could see it running but now it is 2012, I heard that green buses will be on the road by 2010/11 they were but after few months they were removed, It was so convenient that one can move from one place to another in a matter of minutes. Sincere people should come forward, When japan offered them to have all the under ground railways in 90s or before no one looked at it why because all the profit for 20 years would be kept with Japan, Why govt wants to run everything. They should be vigilant on keeping an eye on the contractor instead weather the commuters are being given fair and better services.
What Karachi needs is a full fledged, modern metro rail system like the Delhi or Bangalore metro. Despite the construction of lots of vehicular traffic related infrastructure in the last decade, driving in Karachi is a nightmare. With millions of motorbikes and cars on the roads, it is so stressful that I feel like ripping my hair out each time I drive in Karachi. This KCR project will not be used by the middle class population of Karachi. We need a metro rail system that encompasses all areas of Karachi, rich or poor. That will also bring relief to people affected by rising fuel prices. I will never use public transport until a good quality metro rail system is in place in my city.
Every government makes similar statements in the end of its tenure, including Mustafa Kamal, Naimatullah Khan and their predecessors. It is request to ET not to give coverage to KCR as it is more of rubbing salt in wounds of Karachites.
Too expensive! And it is a loan not a grant or a give away.
Good news for Karachi, finally!!! Thank You Japan.