Reshma power plant only producing 5MW of electricity: CJ
Chief Justice maintains that plant was paid Rs4b and is supposed to produce 200mw of electricity.
ISLAMABAD:
Chief Justice Iftikhar Muhammad Chaudhry, while hearing the suo motu case regarding irregularities in the Rental Power Projects (RPPs), said that the Reshma power plant is producing only 5mw of electricity as opposed to 200mw, reported Express 24/7 on Wednesday.
During the hearing of a suo motu case coupled with two identical petitions involving allegations of corruption in the award of contracts for RPPs, the National Electric Power Regulatory Authority (NEPRA) lawyer revealed that rent is being paid to the projects regardless of their contribution in production of electricity.
The Chief Justice added that the Reshma plant had been paid Rs4 billion and is supposed to produce 200 megawatts (MW) of electricity while only 5mw of electricity is being produced.
However, the lawyer representing the power project said that the plant has already started producing electricity but if required, the company is ready to return the advance amount paid to them.
The CJ also said that the Supreme Court is also reviewing technical faults in the RPPs as the new and old machinery cannot be evaluated on the same grounds.
The hearing has been adjourned till Thursday.
Chief Justice Iftikhar Muhammad Chaudhry, while hearing the suo motu case regarding irregularities in the Rental Power Projects (RPPs), said that the Reshma power plant is producing only 5mw of electricity as opposed to 200mw, reported Express 24/7 on Wednesday.
During the hearing of a suo motu case coupled with two identical petitions involving allegations of corruption in the award of contracts for RPPs, the National Electric Power Regulatory Authority (NEPRA) lawyer revealed that rent is being paid to the projects regardless of their contribution in production of electricity.
The Chief Justice added that the Reshma plant had been paid Rs4 billion and is supposed to produce 200 megawatts (MW) of electricity while only 5mw of electricity is being produced.
However, the lawyer representing the power project said that the plant has already started producing electricity but if required, the company is ready to return the advance amount paid to them.
The CJ also said that the Supreme Court is also reviewing technical faults in the RPPs as the new and old machinery cannot be evaluated on the same grounds.
The hearing has been adjourned till Thursday.