‘Safe City’ inches towards completion

90 per cent of brickwork, 85 per cent plastering of basement, ground, first floor had been completed


Our Correspondent January 14, 2024

RAWALPINDI:

Rawalpindi Division Commissioner Laiqat Ali Chatha visited the Safe City project site and reviewed the ongoing construction working detail.

Regional Police Officer Syed Khurram Ali, Rawalpindi Deputy Commissioner Dr Hassan Waqar Cheema, SE building representatives, Frontier Works Organisation (FWO) project director, and other concerned officers were also present during the inspection.

Read Safe City project still a distant dream

During the visit, the building department representatives informed that 90 per cent of the brickwork and 85 per cent plastering of the basement, ground, and first floor had been completed. The overall work will be completed by January 13 (tomorrow) after which the building will be handed over to FWO for the remaining work, they added.

On the occasion, Chatha said every effort was being made to complete the project before the stipulated deadline of January 30. He said the project will be completed in two phases.

Published in The Express Tribune, January 14th, 2024.

COMMENTS

Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ