He visited the Attaturk Avenue here on Tuesday to inspect the progress of work on the project. CDA chairman directed the Engineering Wing to complete the work on the Avenue from Khyaban-e-Sohrwardi to NADRA Chowk within a week so that the said portion could be opened for traffic. Senior officers of Engineering Wing also accompanied the chairman during his visit.
CDA speeds up work on Ataturk Avenue
Ali was briefed that base and sub-base work from Khyaban-e-Soharwardi to NADRA Chowk has been completed while drainage system has also been established on the said portion. It was also informed that shifting of water supply lines is at final stages while shifting of IESCO services will be also carried out in next few days.
Published in The Express Tribune, July 31st, 2019.