NEPRA approves Rs3.11-per-unit reduction in power tariff
It further listed completion of dam and start of water filling in the reservoir, completion of water way system comprising 51.5-kilometre long tunnels, installation of turbines, generators, transformers and other electro-mechanical equipment in the powerhouse, and dry testing of electro-mechanical equipment, as the infrastructural operational 'milestones' achieved.
NEPRA approves Rs3.11-per-unit reduction in power tariff
"The transmission line by the NTDC is expected to be completed by the end of this month, while water filling (pressurisation) of water way system will commence during first week of January 2018," the release said.
Published in The Express Tribune, December 29th, 2017.