PM rejects proposal to set aside 1,200MW LNG plant

Project is expected to be completed after the end of govt’s tenure


Zafar Bhutta January 13, 2017
The prime minister was of the view that the investors should be given an opportunity to invest in Pakistan even if the project was completed after some years. PHOTO: FILE

ISLAMABAD: Prime Minister Nawaz Sharif has rejected a proposal to abandon a planned 1,200-megawatt LNG-based power plant as it is likely to be completed after the end of tenure of the present government.

The government is working on a plan to set up the 1,200MW LNG power plant in Muzaffargarh, Punjab.

North-South pipeline: Pakistan, Russia reach LNG price accord

In a high-level meeting chaired by the prime minister, a senior official of the Ministry of Water and Power said the premier was informed about progress on the bidding process of the power plant.

Already, the Private Power and Infrastructure Board had approved the project processing framework and request for proposals (RFP) on October 28, 2016.

The board also granted the project one-off exemption from its earlier decision that no new imported fuel-based power plants would be approved.

Additionally, the National Electric Power Regulatory Authority (Nepra) set a benchmark tariff and approved the RFP on November 2, 2016.

Prospective buyers

A pre-bid meeting had been held on November 23, 2016 and six potential investors expressed their interest in the project.

The power ministry official told the high-level meeting that prospective bidders had raised some issues pertaining to the bid submission deadline, the time frame for open-cycle operation, the commissioning date and deadlines for key project activities.

They also requested for waiving the commitment guarantee amounting to $100 million and asked for capping liquidity damages in case of default by international LNG suppliers as per sales and purchase agreement.

PM lays foundation stone of 1,223MW LNG-based power plant

The prospective investors also sought permission for arranging some financing in local currency and suggested that the benchmark tariff should be determined on minimum efficiency of 60% instead of 62.45%.

Plant not included in projection

The prime minister was informed that the 1,200MW to be generated by the power plant had not been included in the power generation projection of the Ministry of Water and Power.

The investors have requested for extension in the deadline for the start of open-cycle operation to April or May 2018 against the government’s target of February 2018.

The power ministry official said the ministry was not willing to accept the investors’ demand for uninterrupted gas supply and waiving the commitment charges of $100 million.

However, the prime minister was of the view that the investors should be given an opportunity to invest in Pakistan even if the project was completed after some years.

He noted that the electricity produced by the plant would be added to the national grid, which would contribute to the economic and industrial growth of the country.

He directed the water and power ministry to push ahead with the project according to the RFP.

Published in The Express Tribune, January 14th, 2017.

Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.

COMMENTS (2)

Rustam | 7 years ago | Reply Forecast for the demand of power, with a little margin for error of forecast, should be the criteria for deciding the addition of the new capacity. For the decided additional capacity, there should be the ranking among the available options. If option of power produced based on indigenous coal is feasible, it should get the first priority. However, the relevant ministry, seemingly,is working like a part of the ruling party instead of in the national interest. It is unfortunate.
Omar Sadiq | 7 years ago | Reply The person suggesting to the PM that the project should be abandoned because the project will be completed after the current govt's term, should be named and shamed and also beaten by the (sleeping) public.
Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ