The prime minister’s foreign affairs adviser Sartaj Aziz said on Sunday that power import through the Casa-1000 electricity transmission project can reach up to 4,000MW.
Aziz’s remarks came a day after Pakistan and Afghanistan signed the agreement on electricity transit fees, in a major step towards energy trading between Central and South Asia.
When completed, Casa-1000 will enable the Kyrgyz Republic and Tajikistan to sell their excess hydropower to fill supply gaps in Afghanistan and Pakistan.
Initially, the Kyrgyz Republic and Tajikistan will export 1,300MW. Pakistan will get 1,000MW of power while Afghanistan will receive the remaining 300MW.
“It is a good agreement for energy connectivity of South Asia and Central Asia. It is a big project and it is just the beginning. And when connectivity is done then the power import through this line can reach up to 4000MW,” Aziz told The Express Tribune.
He said Pakistan at present faced a shortfall of 5,000MW to 6,000MW and the 1,000MW would meet only 20% of its requirements. “It is not enough at present but the project is very good as Kyrgyzstan and Tajikistan are installing new plants and Russia also wants to join the project ultimately,” Aziz said.
He called Casa-100 “a good beginning” for the proposed trade agreement among Pakistan, Afghanistan, Kyrgyzstan and Tajikistan. “When the cooperation begins, it will also pave the way for the trade agreement.”
Casa-1000 will build more than 1,200 kilometres of electricity transmission lines and associated substations to transmit excess summer hydropower energy from existing power generation stations in Tajikistan and the Krgyz Republic to Pakistan and Afghanistan.
To oversee the complex, four-country process, an inter-governmental council has been established to supervise the design and implementation of the project, the finance ministry says.
Asked if the agreed price is in line with Pakistan’s proposal, Aziz said the price is reasonable as Afghanistan had earlier asked for 2.5 cents per KW but after a lot of discussions the price has been brought down to 1.25 cents per KW.
TAPI gas pipeline
Speaking about the current status of the multi-billion Turkmenistan-Afghanistan-Pakistan-India (Tapi) gas pipeline project, he said negotiations are to resume on the project, as had been discussed on the sidelines of the Shanghai Cooperation Organisation (SCO) meeting in Dushanbe.
“Turkmenistan is now inviting project leaders for a survey as to who will be prime financiers to arrange money. Feasibility and other required documents have already been prepared. A tender will be floated after finances are arranged. Then the work can start.”
Published in The Express Tribune, October 13th, 2014.
COMMENTS (7)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ
we will be paying $ 45 million / year for 1000MW as transit fee. We should have been wise like Warid and paid this amount for transit whatever amount of electricity is imported. What about Russian, Chinese and Iranian offers? Is this price comparable to what KP govt is proposing for those small project
This project will give Afghanistan leverage over Pakistan.
They didn't mention the expected completion of transmission lines. However this could be good option for reducing power shortage on temporary basis especially in summer season. The cost seems fairly acceptable too. Not to mention the construction of big hydropower project costs billions of dollars and decade to construct. Smaller projects alteast takes 4-6 years for construction only excluding feasibility, design and contractual processes.
Import everything Dont build dams, power plants, solar plants, wind power projects ect etc but invest in a transmission line that will run through a state called Afghanistan! How sane and great intellect you have Mr. Aziz Or is it the 10% taking over??
And then one day just out of the blues, they can flip the switch and we all can have the massive blackout in our history. Whatever happened to self reliance, I wonder.
If CASA build 1200 KM of transmission line for export to a country, they will also make sure that country will not try to be self sufficient in energy sector. Just like oil exporters to Pakistan dont like hydro power projects to complete. Just like India, that is against hydro power projects in Pakistan but happy to sell power to Pakistan :)
Pakistanis need to wake up and smell the coffee!