Recovery successful: 254MW hydel electricity restored

Despite mountainous terrain and adverse climate conditions, the officials succeeded in energising the line.


Our Correspondent March 15, 2014
Miscreants, in early hours of March 1, blew up the tower of the transmission line in the vicinity of Battagram in Khyber-Pakhtunkhwa. PHOTO: FILE

LAHORE:


Following the re-erection of the blown-up tower of 220-KV Allai-ISPR-Tarnol Transmission Line, Khan, Allai and Duber Khwar Hydel power stations have once again started providing 254 Megawatt (MW) of much-needed low-cost hydel electricity to the national grid.


The miscreants, in early hours of March 1, blew up the tower of the transmission line in the vicinity of Battagram in Khyber-Pakhtunkhwa, disrupting the power supply from the three high-head hydropower projects. It may be mentioned that it was the second incident relating to blowing up of a tower within a fortnight.


Soon after the Water and Power Development Authority (Wapda) and National Transmission and Despatch Company undertook the restoration task of the transmission line. Despite mountainous terrain and adverse climate conditions, the officials succeeded in energising the line.


Published in The Express Tribune, March 16th, 2015.

Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.

COMMENTS

Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ