The Hub Power Company announced its financial results for the nine-month period of fiscal 2013 on Thursday, posting a profit 49% to Rs7.4 billion compared to Rs4.97 billion in the corresponding period of last year.
Hubco is engaged in the electric utilities industry. The company owns an oil-fired power station with an installed net capacity of 1,200 megawatts (MW) at Mouza Kund, Hub, in Balochistan; and a 225MW capacity oil-fired power station at Mouza Poong, Narowal, in Punjab. The company also has a 75% controlling interest in Laraib Energy, a subsidiary that is developing an 84MW hydel power plant.
Topline Securities analyst Nauman Khan believes that earnings growth in the nine-month period primarily stems from commissioning of the Narowal project.
Moreover, another factor, he said, that played its role in growth of profits was the “U-shaped” based return while higher indexation factor – rupee depreciation and inflation.
In the first quarter of fiscal 2013, Ayaz Ahmed of Global Securities says that Hubco’s main plant propelled the earnings, which he expects to operate at a load factor of 78.4% (2,302 gigawatt hours), where Narowal’s utilisation remained subdued at 27% (128 GwH) due to piled-up receivables of Rs19 billion, which has partly rendered the plant un-operational.
Revenues improved to Rs132.49 billion in the nine-month period, gross margins improved 100 basis points to 9.6% and finance costs shrunk to Rs5.04 billion during the period under review.
Published in The Express Tribune, April 26th, 2013.
Like Business on Facebook to stay informed and join in the conversation.
COMMENTS
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ