The Neelum-Jhelum Hydropower Project is likely to be completed about two years ahead of schedule now that Tunnel Boring Machines (TBMs) have reached the site.
Official sources in Wapda said that the TBMs were imported from Germany at a cost of around Rs8 billion and would expedite the excavation of 32- kilometre long water tunnels.
Pakistan would join the club of hi-tech countries which use the machinery for excavating tunnels. The sources said construction work was under process on the project round the clock to ensure completion of the project by June 2016.
The 969MW Neelum-Jhelum Hydropower Project is part of Wapda’s low cost generation programme, being implemented on a priority basis. The project is being constructed over Rivers Neelum and Jhelum in Azad Jammu and Kashmir.
The project will contribute about 5.15 billion units of electricity annually to the national grid. Annual benefits of the project have been estimated at Rs45 billion.
Published in The Express Tribune, February 29th, 2012.
COMMENTS (4)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ
One despairs of negative comments even when the news has something positive in it.
Completing a project of this complexity on time and on cost is a rarity. Completing it before schedule would be a most welcome outcome. Let us hope that there are no slippages.
@khan: so you are an indian LOL
whats the point in spending this extra money and sell more stake to the chinese? The Indians have deployed TBMs early 2011, and almost 70% of the work is done on Kishanganga. They are well on track on finish the project by 2.. its a 2014-15 frame, and will retain the rights on the river. Even International Arbitration have allowed India to continue construction... In my mind, we can finsih by 2016, 17, 18.. its a game lost as usual...