Sindh plans major water supply project for Thar

Proposals include laying of 36-inch pipeline from Naukot to Mithi, restoring RO plants


Sajid Bajeer November 22, 2026 1 min read
Tharis on the move as drought drives livestock exodus

MITHI:

The Sindh government has started planning emergency and long-term measures to address drought and severe water shortages in Tharparkar following a prolonged lack of rainfall. Proposals include laying a new 36-inch-diameter water supply pipeline from Naukot to Mithi, restoring non-functional reverse osmosis (RO) plants and introducing a revised water distribution schedule.

A meeting in this regard was held at the deputy commissioner's office in Mithi with Special Assistant to the Sindh Chief Minister on Public Health Engineering and Rural Development Muhammad Saleem Baloch and Parliamentary Secretary for Local Government and MPA Qasim Siraj Soomro in the chair. Secretary Public Health, Deputy Commissioner Tharparkar Abdul Haleem Jagirani, district and taluka officers, and engineers from relevant departments attended the meeting.

The meeting reviewed the drought situation, availability of drinking water, water supplies for livestock and ongoing development projects across the district.

Briefing the media after the meeting, Saleem Baloch said that the total dissolved solids (TDS) level in Tharparkar's groundwater ranged is very high, making it unfit for human consumption in most areas. He added that nearly 50 per cent of the district's 832 RO plants were non-functional.

He said the government had decided to assess the condition of all RO plants, restore those out of order and introduce a mechanism for their regular maintenance.

Currently, water is supplied from Naukot to Mithi through a 12-inch-diameter pipeline, but the existing system has become inadequate due to population growth and increasing demand. Mithi alone requires around 1.4 million gallons of water daily.

To address the crisis permanently, the government is considering laying a 36-inch pipeline from Naukot to Mithi, a 24-inch pipeline from Mithi to Islamkot and an 18-inch pipeline from Islamkot to Nagarparkar. A final decision will be taken after consultations with Chief Minister Syed Murad Ali Shah and the party leadership.

Until the proposed project is completed, a revised water distribution schedule has been suggested under which Mithi and Islamkot will receive water for two days, and Nagarparkar for one day to ensure a more equitable distribution of the available supply.

Saleem Baloch said that after their repair and restoration, RO plants would be handed over to local communities for maintenance. Village Development Associations would be established in the respective villages to oversee their upkeep. He urged residents to consider the plants their own assets and play an active role in protecting and maintaining them.