Water projects slip down priority list in Sindh budget

Just Rs150m set aside for Karachi’s 65 MGD water project, meagre Rs50m allocated for K-IV project


Syed Ashraf Ali June 19, 2020
A representational image. PHOTO: REUTERS

KARACHI: While Karachi finds itself at the centre of a water crisis that has been worsening for years now, the Sindh government has apparently put the city's water needs on the backburner, setting aside just Rs150 million for a 65 MGD excess water project in the provincial budget for the coming year.

The project, which was approved in 2014 and construction for which began in 2017, was planned so that it would reach completion within two years. However, it has remained in limbo for the past year, mainly due to lack of funds and the government's apparent lack of interest.

Considered crucial for overcoming the prevalent water scarcity in Karachi, it is now likely to face further delays with the government failing to allocate sufficient funds for its completion.

Similarly, just Rs50 million has been earmarked for the much-vaunted K-IV bulk water project, which was initially to see its completion in 2018.

Karachi needs 1,200 million gallons of water daily to sustain the needs of its population. However, the city is only supplied with 406 MGD of water. Under the distribution system of the Karachi Water and Sewerage Board, 364 MGD and 42 MGD of water is provided for domestic use and the industries, respectively.

Improving water and sanitation

In a bid to improve the water supply and sanitation system, the government has earmarked Rs50 million for the construction and repair of filter plants at Gharo, Pipri and COD, as well as North East filter plant, running under the KWSB. Once rehabilitated, the plants will improve water filtration for Karachi by 210 MGD.

Apart from this, Rs15 million has been set aside for the construction of new filter plants in Karachi, while Rs62.5 million has been allocated for the upgrading of the K-III, K-II and NE pumping stations, Rs62 million for the upgrade of Hub pumping house and pumping station, Rs37 million for the upgrade of Gharo pumping station and Rs25 million for the upgrade of Damloti pumping station.

Separately, Rs37.5 million has been kept for laying down water pipelines in Defence Housing Authority, Qayyumabad and other areas.

Besides, the Sindh government has earmarked Rs18.7 million each for all six districts of Karachi, to spend on the repair and replacement of water and sewerage pipelines.

As much as Rs100 million has been set aside for the procurement of machinery and sewerage cleaning in Karachi. In addition to this, sums have also been allocated for the construction and repair of various roads and drains across the city.

Rehabilitation schemes

The provincial government has also announced Rs330.11 million for the Competitive and Livable City of Karachi Project, which it has launched in collaboration with the World Bank (WB). The project, aimed at carrying a property survey of the metropolis and enhance its living conditions, is to cost Rs33.6 billion, of which Rs32.2 billion will be paid by the WB and Rs1.4 billion by the Sindh government.

It has further reserved Rs25 million for controlling environmental pollution at Clifton Beach and to protect and preserve marine life.

Solid waste management

Besides, the government has set aside another Rs330 million for establishing six garbage transfer stations in Karachi. Moreover, Rs240 million has been allocated for the establishment of two landfill sites, Rs23 million for a feasibility study pertaining to hospital waste management and Rs26 million for a study pertaining to industrial solid waste management.

KWSB overhaul

Furthermore, the government has earmarked Rs70 million for the first phase of Karachi Water and Sewerage Services Improvement Project, which has been initiated to make the water board a viable utility.

Jointly launched with the WB and Asian Infrastructure Investment Bank (AIIB), the project is to cost around Rs14.7 billion, of which Rs5.8 billion is to be paid by the WB and as much by the AIIB, while remaining Rs2.9 billion is to be furnished by the Sindh government.

The government has separately earmarked Rs22 million for carrying out a study of the project, so that a project implementation unit can be set up.

Published in The Express Tribune, June 19th, 2020.

COMMENTS

Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ