Pakistan gets $425 million loan to modernise transmission network

Signs agreement with World Bank that also provides $140m for Sindh barrages


Our Correspondent June 14, 2018
The existing transmission system has the capacity to carry about 15,000-17,000 megawatts of electricity safely, which is substantially below the peak load of over 20,000MW, according to the World Bank. PHOTO: REUTERS

ISLAMABAD: Six months after its approval, Pakistan and the World Bank on Wednesday signed a $425-million loan agreement for bringing improvement in the country’s dilapidated electricity transmission network.

Economic Affairs Division Secretary Syed Ghazanfar Abbas Jilani and World Bank Country Director Patchamuthu Illangovan signed two agreements worth $565 million. These included a credit of $425 million to modernise the power transmission system and additional financing of $140 million for the Sindh Barrages Improvement Project.

Caretakers to brief nation today on power outages

The $425-million loan has been acquired on commercial terms that will be returned over a period of 21 years including a grace period of six years. The World Bank board had approved the loan in December last year, but the bureaucracy took six months to meet procedural requirements before signing the agreement.

The loan will be spent on modernising the national transmission network by rehabilitating selected 500-kilovolt and 220kv sub-stations and transmission lines.

The existing transmission system has the capacity to carry about 15,000-17,000 megawatts of electricity safely, which is substantially below the peak load of over 20,000MW, according to the World Bank. The objective of the project is to increase capacity and reliability of selected segments of the national transmission system and modernise key business processes of the National Transmission and Despatch Company (NTDC).

Aging and inadequate transmission and distribution systems exacerbated the problem. The World Bank said Pakistan’s recent efforts had been focused on increasing power generation capacity, but aging and increasingly unreliable transmission and distribution systems also imposed severe constraints.

There have been several instances of major system collapses, which appear to be increasing in frequency and severity.

In the distribution system, two key measures of system reliability, the System Average Interruption Duration Index (SAIDI) and the System Average Interruption Frequency Index (SAIFI), present a mixed picture, but suggest that in several distribution companies the quality of supply is deteriorating.

PML-N govt responsible for resolving Karachi’s electricity woes: Bilawal

The regulator reports that most distribution systems do not meet the investment targets for repair and maintenance.

The project will support investments in high-priority transmission infrastructure, information and communication technology (ICT) and technical assistance for improved management and operations.

Total cost of the project is $536.33 million. The World Bank will provide $425 million whereas the remaining $111.33 million will be arranged by the NTDC.

The project targets include a three-fourth reduction in forced outages and 50% reduction in the frequency of forced outages. About 131-kilometre-long transmission lines are planned to be rehabilitated and 36 new sub-stations will be constructed.

Under the Sindh Barrages Improvement Project, the development objectives are to improve reliability and safety of the Guddu Barrage and strengthen the Sindh Irrigation Department’s capacity to operate and manage the barrage.

This additional financing will help to scale up activities under the original project, whose scope at present is limited to rehabilitating and modernising the Guddu Barrage.

Now, the project will also support rehabilitation and modernisation of the Sukkur Barrage as well as support improvement in the operation and maintenance of three Sindh barrages over the Indus River - Guddu, Sukkur and Kotri - through better coordination and monitoring.

World Bank sees Pakistan’s economy slowing next year

Total estimated additional financing required is $152.2 million and the remaining $12 million will be provided by the government of Sindh.

Published in The Express Tribune, June 14th, 2018.

Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.

COMMENTS (2)

Menon | 5 years ago | Reply $25 million goes towards modernization and $400 million evaporates!
Engr.Amir Sultan Rana | 5 years ago | Reply A good step forward. Pakistan should move forward to keep them align with the modern time and be updated in the electric transmission area too. Best of luck to Pakistan.
Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ