An executive of a contracting company told The Express Tribune that all construction works near heritage sites had been halted since January 28, 2016, when the court issued the first stay order. The court took almost 22 months to announce its verdict about the project's fate. This not only delayed the scheme, but caused huge financial losses to the public exchequer.
He disclosed that In a recent progress review meeting of the project, a chief engineer indicated that the delay was costing the public exchequer around Rs20 million on a daily basis. "Neither local nor Chinese contractors have estimated the exact magnitude of loss, but they will submit their claims once the project is completed."
Mass transit: OLMT enters completion phase
He pointed out that the government generally negotiated such claims with local contractors to minimise its burden of loss, but in international contracting, it is difficult for the client to reduce such liabilities. According to an estimate, the delay already cost the public kitty over Rs10 billion, but an exact amount of loss will surface on completion of the project," he underlined.
Responding to a question, he said it was impossible to complete the metro train project before the general elections in 2018. "The central station near Mall Road is the most critical infrastructure of the project for both Pakistani and Chinese contractors. It is a three-storey underground structure with tonnes of equipment and systems to control the entire metro train operations, but no work was initiated at the site yet due to the court's stay order," he said. He added that Chinese engineers also required a lot of time to complete electrical and mechanical works as they have hardly completed 30% of the target.
OLMT Package-1 (from Dera Gujjran to Chaburji) and Package-2 (from Chaburji to Ali Town) contractors said though it was a challenging task, they would try their level best to complete the project in the minimum time. Package-1 contractor Shahid Saleem said he needed more than two months to complete the elevated portion of the metro train track after which Chinese engineers would lay rails and complete electrical and mechanical works. "I believe metro train track will be ready from Dera Gujjran to Lakshmi Chowk by the end of March 2018. The most difficult and time-consuming section of the Package-1 is central station for which we have to close Mall Road for all types of traffic."
Replying to a question, he said construction near heritage sites would start after installation of seismic sensors on historic sites as directed by the apex court. It will take a little time to initiate construction activity near the famous Shalimar Garden as utility companies have to shift underground wires and pipes from the site.
OLMT construction disrupts gas for 12 hours
The OLMT Package-2 contractor, Chaudhry Waseem Afzal, said his company has targeted completing and handing over the elevated metro train track to Chinese engineers for installation of rails and other equipment by the end of February. He was of the view that the completion of metro train project is dependent on works that will be carried out by Chinese engineers.
OLMT Steering Committee Chairman Khawaja Ahmad Hassaan, on Saturday, chaired a special meeting to chalk out a comprehensive plan to complete the metro train project in minimum time, besides initiating the process to constitute three special committees for the project, as per directions of the Supreme Court.
He said a formal request has been made to the Chief Justice of Pakistan to nominate a retired judge of the superior judiciary as a member of the ‘supervisory and monitoring committee' for the project. He reiterated that the directions by the apex court will be implemented in letter and spirit.
He said a high-level delegation of Chinese contractor CR-NORINCO will arrive Lahore on December 15 to negotiate “operation and maintenance contract' for the project”. Hassaan added hurdles in the completion of this project have been removed as a result of the landmark judgment of the SCP. “Now a challenging task is to complete the project is the shortest interval.” He urged all relevant departments and agencies to intensify efforts and work day and night for the early completion of this project.
Published in The Express Tribune, December 10th, 2017.
COMMENTS (1)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ