Earlier, the government had committed to paying $50 million to the contractor of Tarbela-4 extension project if it succeeded in completing work by June 2017. However, the contractor appeared to be unlikely to meet the time frame.
Diamer-Bhasha project: PM approves in principle financing plan for dam
It is surprising that taxpayer money was paid as an incentive to the contractor, who got $25 million. Now, the government is seeking to recover the money.
Wapda Chairman Muzammil Hussain sought a review of the government’s decision to demand $25 million from the contractor out of the committed $50 million, according to Wapda sources.
Officials in the authority revealed that in a high-level meeting on November 29, chaired by Prime Minister Nawaz Sharif, the Wapda chairman called on the government that it should review its decision as the recovery of $25 million already paid to the contractor would not be easy due to various reasons beyond the control of the contractor.
Five regulatory bodies stripped of autonomy
He also requested that Wapda should be allowed to undertake the work acceleration programme.
In a huddle on September 15, the secretary to the prime minister had stated that the issue of payment for early completion of the project should be settled as despite receiving the incentive, the contractor did not live up to the commitment. Therefore, he said, measures for recovery of the money should be explored.
Consequently, the premier directed the Wapda chairman to take necessary measures for recovering the amount paid.
The Wapda chief updated meeting participants on the progress made so far on the Tarbela-4 hydroelectric power extension project.
Three units of 470-megawatt each with total capacity of 1,410MW were being installed on the Tarbela-4 tunnel, which would enhance overall capacity of the Tarbela power station to 4,888MW compared to earlier 3,487MW.
Tarbela-4 extension: Govt looking to recover $51m from contractor
The original deadline for completing work on the project was February 2018, but for accelerating work and making the project ready by June 2017, a variation order was signed and payment made to the contractor.
Despite the incentive, the contractor seemed unlikely to complete the project by the set time frame because of the pace of work so far.
Earlier, Finance Minister Ishaq Dar, in a meeting of the Cabinet Committee on Energy held on August 30, 2016, had also raised the matter of payment made for the Tarbela-4 acceleration plan.
Since the project would now be commissioned according to the original plan, the amount already released for the contractor needed to be recovered, he said.
Water and Power Secretary Younus Dagha pointed out that instructions had been issued to Wapda in that connection.
Tarbela 4th Extension: WAPDA chief calls for speedy completion
The prime minister was told that former Wapda chairman had made a commitment that the Tarbela-4 extension would start functioning by August 14, 2017. However, the premier expressed displeasure over the slow progress and directed the water and power secretary to firm up a time frame with the newly appointed Wapda chairman.
Published in The Express Tribune, December 27th, 2016.
Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.
COMMENTS (7)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ