Dasu hydropower project: Work delayed as issues remain unresolved

Authorities have failed to address matters relating to the cost of land, site security and fund allocation


Shahbaz Rana August 15, 2015
The government has preferred 4,320MW Dasu hydropower project over Diamer Bhasha Dam. PHOTO: FILE

ISLAMABAD:


The prime minister's desire to inaugurate the first phase of 2,160-megawatt Dasu hydropower project before his constitutional term ends will remain unfulfilled as the project execution authorities have so far failed to resolve issues pertaining to the cost of land, security of the site and channelling of funds.


The government has preferred 4,320MW Dasu hydropower project over Diamer Bhasha Dam and Prime Minister Nawaz Sharif is keen to inaugurate the first phase before the end of his five-year term in 2018.

In June 2014, the premier had performed the groundbreaking ceremony for the first phase. However, sources in the Ministry of Water and Power revealed that inept bureaucrats were unable to handle the project, which may also become a reason for the World Bank to delay loan disbursements.

The World Bank's financing is critical for timely completion of the first phase of the project that has a total cost of $4.3 billion. The bank has already approved $588.4 million for the mega scheme besides giving guarantees for another $460 million.

Read: Dasu Hydropower Dam to be completed by 2020, NA told

According to a project appraisal document, the WB has promised to extend guarantees for obtaining $1.9 billion in commercial loans. In addition to this, it also plans to approve another loan of $533.4 million for the project by next year provided the scheme advances as per schedule.

Because of the bureaucratic hurdle, the timeline for the project has been set back. The government has asked Water and Power Development Authority (Wapda) to complete the first phase in three years but the authority's assessment is that it cannot be completed before 2020.

Hurdles in the way

In order to discuss the outstanding issues, a meeting of the Dasu steering committee was held earlier this week at the Ministry of Water and Power.

World Bank's Lead Water Resources Specialist Masood Ahmed, who is currently visiting Pakistan, led the bank in the review meetings. Ahmed also met Finance Minister Ishaq Dar on Thursday, seeking his intervention to resolve the issues.

The steering committee discussed the problems relating to the price of land, finalisation of security contract for the protection of dam site, decision on construction of a transmission line for linking the generation site with the national grid and placing funds in Escrow accounts.

According to sources, no breakthrough was achieved during the meeting and all issues were left to be decided by Finance Minister Dar.

"Although it is not the direct responsibility of my ministry, I will resolve all the outstanding issues to keep the project on track," said Dar while talking to The Express Tribune.

He said another meeting would be held by the middle of next week in which these issues would be resolved.

Dar said the security cost was covered in the PC-I document of the project and it should not be an issue. His ministry has also sorted out the matter related to funding.

Wapda Chairman Zafar Mehmood wanted that the security job should be performed by the police, according to a senior Wapda official working on the project. However, he said police refused to perform this duty.

If these issues remain unresolved by the end of this month, the World Bank may declare the project unsatisfactory, said sources.

Read: WAPDA signs two contracts with Chinese company

The Wapda official claimed during the steering committee meeting, the issue of land cost was also resolved to the satisfaction of the deputy commissioner of the region, who would now negotiate with the locals. He said the transmission line issue would be resolved by the end of this year.

Wapda is also facing problems in moving the contractors to the site. The Wapda official said one contractor had been mobilised while two contractors would be mobilised by the middle of next month.

Published in The Express Tribune, August 15th, 2015.

Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.

COMMENTS (2)

IBN E ASHFAQUE | 8 years ago | Reply Sharifs, Altaf, Zardari and that cricketer joker are the curse that ordinary Pakistanis have to endure in the name of democracy, through which they hope to achieve salvation in this world. May Allah guide them.
Chachoo | 8 years ago | Reply I have closely worked with Sharifs in the past. Believe me they are one of the worst as they are not the sincere of Pakistan but they are clever enough to rule this land. They just want to take the whole credit. Both Sharif brothers have a simple thinking that never to pursue the project of any other and become a hero by inaugurating everything on their own. Sialkot-Gujranwala motorway project was scrapped because it was conceived by Pervaiz Ilahi. Then Shahbaz Sharif is the worst enemy of Rescue 1122 as it was not conceived by him. Now rescue 1122 is begging the people to give them funds as Shahbaz is not providing them funding. Similarly Bhasha dam was conceived in the previous government and Nawaz Sharif cannot take its credit. So in order to take credit he will do whatever it takes to start the Dasu project. Bhasha dam has the full feasibility completed. But Nawaz Sharif cannot enjoy the full credit so our Mughal king will never go for that project.
Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ