Mayo Hospital: Delayed ventilation system project raises questions

Medical superintendent denies irregularities in contract award.


Anwer Sumra December 07, 2011

LAHORE:


A Rs36 million contract for the installation of a heating, ventilation and air conditioning system in Mayo Hospital’s emergency ward was awarded and paid in full in advance in violation of the rules, and the work has already been delayed by several months, The Express Tribune has learnt.


The Health Department awarded the contract to Pak Elektron Limited (PEL) in April, though a lower bid of Rs30 million had been made by a competitor, said an official.

The entire payment was made in advance, in violation of Punjab Financial Rules and Subsidiary Treasury Rules, on the orders of the then health secretary (Fawad Hasan Fawad), said the official.

The annual audit of Mayo Hospital for 2010-11 includes an audit para – a note from the auditor – stating that there were major irregularities in the installation, commissioning and purchase of the HVAC system. The matter is with the Public Accounts Committee of the Punjab Assembly.

The department invited bids for the project in November last year and MIA Corporation, Haier, PEL and Sabro applied. According to the official, PEL quoted a price of over Rs50 million while Sabro offered to do the job in Rs30 million. The contract was eventually awarded to PEL for Rs36 million.

A purchase order was issued on April 28 and the contractor was given 180 days (until October 28) to have the heating, ventilation and air conditioning up and running.

The medical superintendent of Mayo Hospital, Dr Zahid Pervaiz, issued a cheque for Rs30 million to PEL on May 10, and a cheque for Rs6 million on June 15.

These payments were made on the orders of the health secretary, said a senior hospital official.

The payments were made in violation of the Punjab Financial Rules and Subsidiary Treasury Rules, said an official of the Finance Department.

The contractor began civil and engineering works at the Emergency Block in May, but has fallen behind schedule. Only air ducts have been installed so far, and a hospital official claimed the copper sheeting used in their making did not meet the technical specifications approved by the Health Department.

Amjad Iqbal, general manager for Sabro, alleged that the health secretary had “hidden motives” to disqualify his firm.

“Sabro submitted the lowest bid with the correct technical specifications. There was no justification for awarding the contract to another firm. We wrote to the health secretary about it but he ignored us,” said Iqbal.

A doctor at the emergency ward complained that the work on the ventilation system was a hindrance to his work due to the noise and mess. He said the emergency block, which has 200 beds, gets over a thousand visitors a day.

A PEL employee said on the condition of anonymity that it would take another three to four months to complete the project. He said the import of equipment had been completed, apart from cooling towers and chillers. He said the project had been delayed because the work was suspended during the dengue outbreak.

Zahid Pervaiz, the Mayo Hospital medical superintendent, said the contractor would have to pay a penalty for the delay.

He said that the contractor had demanded advance payment and the steering committee for the project had approved this.

He said that the Sabro bid was disqualified on technical grounds and the deal with PEL had been approved by the authorities concerned.

He said the project was now due to be finished this month.

PEL manager Kashif Maqsood, who was present on site, refused to comment.

Published in The Express Tribune, December 8th, 2011.

COMMENTS (2)

Fire Free Engineers | 12 years ago | Reply

INTRODUCTION:- Fire Free Engineers was established as a trading and consulting company specialized in Fire and AIR VENTILATOR Engineering and maintenance of the fire fighting equipments. Fire Free is totally dedicated with AIR VENTILATOR as a trading unit. The firm has the ability to meet the challenges AIR VENTILATOR presented by the ever increasing technological advances. With its highly trained and competent field supervisors directing the skilled workers on site, Fire Free Engineers will always ready to meet any challenges. At Fire Free Engineers, we value our customer’s business and we strive to return that value to them through quality and service. Our firm is built on foundation of Quality and Service to our customers. sale manager MR afzal tade

Sikander Khan | 12 years ago | Reply

Dear Sir, I am graduate in 1973 in mechanical Engineering, and please note my overseas experience is over 35 years, and now back in Pakistan. I have worked on "Hamad General Hospital" - 1000 beds hospital in Doha, State of Qatar,as HVAC Site Engineer, and worked from 1975 upto 1984. Especially I am specialist in Operations Theaters. My full technical support and advise for you always without any fee for any hospital in Pakistan. Please do not hesitate to contact me at any time. Kind regards. Sikander Khan from Karachi

Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ