Country’s largest steel making concern has to pay around Rs930 million to the Karachi Electric Supply Company (KESC) against payment of power purchases from March to April 2013.
Officials of the two organisations had a meeting at the KESC head office for two hours to resolve the crisis, but ended on a stalemate.
While the KESC insists that PSM immediately pays at least Rs550 million, PSM is willing to pay just Rs250 million during the month.
PSM suggested proposed increasing the daily payments to Rs15 million from Rs10 million but KESC refused to accept, saying this arrangement will take a long time to clear the backlog.
A PSM spokesperson said that they were trying to convince KESC to restore power supply to at least the residential colonies of the mill.
“We have to rely on national power grid to run our steel rolling mills. But the blast furnace and coke oven batteries are running on our own thermal power plant,” he said.
In the meeting, KESC also sought letter of comfort on behalf of Ministry of Finance as an assurance that it will get the dues but PSM refused to furnish that.
The problem of non-payments goes on to show that power crisis has gone beyond control.
Published in The Express Tribune, July 19th, 2013.
Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.
COMMENTS
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ