Shops in Muslim Town are continuing to lose business because of the government’s failure to complete the service roads around the Muslim Town flyover, which was inaugurated on May 30.
The disruption to their businesses has gone on since September last year, when work on the flyover began and traffic on Ferozepur Road was diverted to the service lanes. The service roads crumbled due to heavy traffic loads including heavy machinery used in the construction.
Though the flyover was officially inaugurated six weeks ago, the service roads under the flyover are still unrepaired. Further, workers are now building an elevated bus lane for the Metro Bus Service project, formerly known as the Bus Rapid Transit System. With that work due to take at least six months, the businesses have been left wondering about their future.
Hafiz Zubair, the owner of Delite Store, said that business had never been so bad in the 42 years since he had opened the store on Wahdat Road. “I would say our sales are 30 per cent of what they used to be before the construction of the flyover began,” said Zubair.
He said that most of his clientele were from Ichhra and Canal Bank Road and they had stopped coming after the road was broken up. He said that some shop owners had formed unions and approached the government, which had repaired patches of road in front of their shops, but most of the road was still a mess.
Malik Ayaz, the owner of Rafiq Sweet House, said that they had been losing business since the start of the flyover project. “We had hoped the situation would improve after the inauguration of the flyover, but they haven’t repaired the road at ground level,” he said.
Wajid Butt, the general manager of the popular Butt Sweet House, said that the business was operating at 50 per cent of the level it was at last year. He said that he did not expect things to improve soon. He said that the government had not communicated any deadlines for the repair of the roads to the shopkeepers.
Sabir Khan Sadozai, the project director for the Muslim Town flyover, said that the repair of the service roads had initially been delayed because the Water and Sanitation Agency had to lay a sewage line. Then the Traffic Engineering and Transport Planning Agency (TEPA) stopped the repairs as the final design of the elevated bus lane for the Metro Bus Service, being drawn up by the National Engineering Services of Pakistan (NESPAK), had not arrived. “Otherwise we could have had a situation where we finished the reconstruction of the road but TEPA had to break sections of it again to lay piers for the elevated bus lane,” he said.
Sadozai said that the design of the bus lane had been received from NESPAK last week and they had started the road works. He said that WASA still had some work to finish, namely to raise the height of gutter necks on Wahdat Road and Ferozepur Road so that the manholes were at the same level as the road. He said that work on the service lane around FC College and the 1122 office would be finished in a few days. He said some sections of the road would not be repaired until after the bus lane is finished.
Asked why the design of the bus lane for the MBS project had been changed and delayed, TEPA Director Mazhar Hussain, who is in charge of the construction, said that the decision had been made to avoid the expense and hassle of having to acquire land for a ground-level bus lane.
Published in The Express Tribune, July 16th, 2012.
COMMENTS (6)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ
surprise....in India such news would not deserve a fleeting reference in international media.
@Amjad
please come to Rajanpur district and Jampur and show me a single piece of PML(N) developmental work.
Truth is all work is in Lahore and all funding of Punjab is used in Lahore.
@LuvlySingh..: Come to the Punjab and you will see that not only Lahore but the whole province has benefitted from his rule. Not only in Lahore but all cities in the Punjab are developing due to the initiatives taken by the CM. Ask yourself what province in Pakistan has the most growth and stability and that too when the federal government is actively denying energy.
is he the CM of Punjab, or lahore only?
Good riddance. Wahdat road was always blocked due to the their customers parking.
From Phajja to all the way to Good Luck bakery, they used the service lane for parking and sitting arrangements of customers. All these shop keepers along Wahdat road used the service lane for parking of their customers and at some places encroached upon for merchandising products.
You can't please all of the people all of the time but the majority of people in Lahore welcome the infrastructure projects since they have transformed the city making commuting times much more manageable. There are bound to be some people who will be adversely affected but it is important to consider the benefit enjoyed by the majority.