Out of order since 2006, two units of the Lakhra Power Plant – the only coal-fired power plant in Pakistan – will continue to be nonoperational since the Water and Power Development Authority has not disbursed the plant’s maintenance fund, apparently due to a leasing dispute.
According to sources, two units of 50 megawatts each of the Lakhra Power Plant – based in Lakhra coal field, Dadu District of Sindh – had been out of order and not maintained at all since 2006 over a leasing issue, leading Wapda, which operates the plant, to cease funding the plant’s maintenance.
In 2006, the plant was leased to Jamshoro Joint Venture with the understanding that the machinery and staff of the plant would remain under Wapda’s jurisdiction while JJV will invest in power generation and overhauling of the plant.
The labour union at the plant, however, challenged the lease of the plant and managed to get stay orders from the Sindh High Court. The SHC eventually decided in favour of JJV, following which the union took the case to the Supreme Court, which has yet to decide the case.
In 1995, the China-based Dongfang Electric Company (DEC) had constructed the plant with three units of 50MW each. DEC had recommended that all three units should go through a complete overhaul every four to five years; the source said. He added the Chinese firm also recommended that each plant should operate for three weeks and remain closed for maintenance in the last week. Coal dust damages the tubes of the machinery, which requires regular maintenance.
Both the units are in desperate need of rehabilitation. Nevertheless Wapda has so far refused to spend anything to fix the broken-down units unless the Supreme Court gives its verdict, a source familiar with the matter said.
Wapda could fix these units but they are scared that the change in government may hand it over to some private company again, said another source whose company provides coal to the plant.
While they admit that maintenance funds have not been released for the two units, Wapda officials ruled out the possibility of any technical issues.
“There is no technical problem with the plant,” said Ghulam Hussain Dahree, Wapda’s resident engineer at the thermal generation facility. “We have both coal and limestone available for production. The only problem is of funding without which the units cannot be made operational,” he said.
The plant was closed in 2006 when it was leased to JJV, Dahree said. “The maintenance expense has become an issue since then,” he added. However, he explained that Wapda has decided to run the third unit and bear all of its expenses. Regarding the lease issue, he said, there has been some progress in the case and another hearing is scheduled this month.
The project – that included Lakhra Coal Mine and Lakhra Power Generation Plant – was proposed in 1986 to meet the then energy requirement of the country. According to the proposal, the coal mine had to be developed and operated by private sector companies while the power plant had to be operated by Wapda. The proposed plants were to have a capacity between 300MW and 700MW.
The closure of two units has deprived the national grid of at least 60MW as none of the units could meet its production capacity of 50MW. Talking about the capacity of these units, Dahree said, the Chinese plants are usually of capacity up to 25MW while those at Lakhra Power Plant were designed to produce 50MW on a trial basis.
“Even when Chinese engineers were here, the plant did not work on full capacity,” Dahree said, “so they decided to reduce its output to 40MW for each unit.”
According to sources, the third unit – which has also been closed recently for regular maintenance – was producing between 30MW and 35MW. Dahree, however, said these units can produce 40MW and can be upgraded to meet 50MW – a target these units were designed to meet.
Published in The Express Tribune, January 4th, 2012.
COMMENTS (17)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ
It is oveall bad command of WAPDA.I visited this plant in 1999~2000 in good working condition at that time two boiles were in opation & one was uder maintenance. I am working here at OLYMPIA CHEMICALS LTD, SODA ASH PLANT, as a Sr Dy Manager Mechanical since1998, having three coal fired boilers 20,20 & 35 ton capacity resectivly & one 75 ton capacity boiler is under errection.No problum at all from couples of years. So many modifcatons has been done by our team day by day..
Speechless!
Poor management by incompetent leaders put in to power by us. I do consider myself and my fellow country men responsible for this.
@Z Ali: I have forgotten neither, as i remember when Zia came to power, i was at Uni, and did discuss this with few pakistani friends of mine about it. But the sad fact is that Pakistan, since its creation has always had Military as the principal institution in the country rather than parliament, elected by the people. So whenever the Army has ruled the country, the majority of resources have been diverted to their causes rather than main stream of society, hence the situation. One only has to look at Army's commercial operations in the country, to realise that thereis no other Army in the world perhaps as commercialised as Pak Army. In regards to Pakistan's political parties , well they have learned nothing much and are very much a family businesses, just like the congress party in India, however indian political scene is different, in terms that the institution still works even with its flaws, where as in Pakistan the outgoing party leaders are always likely to end up in Jails on sume charge or other and majority of time, they ousted by the Army.
Pakistan Zindabad. India has worse problems than this and Indians should stick to their own problems and news websites !!!
@hedgefunder: Actually that is precislely the problem: We do NOT choose our government... for far too long the West has maintained its cosy alliances with dictators in Pakistan to do their bidding.. or have you forgotten Zia ul Haq and Parvez Musharraf???
Someone please kindly make government and supreme court read this news and tell them that we have more pressing issues to be resolved than political issues/cases. Entire government, media and judiciary is busy dealing with politics and no one is bothered about the issues People of Pakistan are facing.
My fellow country men and women its about time we stop crying on our past mistakes we have learned traditional political parties have betrayed us . We should give chance to Mr Imran Khan to see and solve all our problems and if he dont then we loose nothing because we have nothing to loose May God Bless our new leader Pakistan Zindabad
Cant fault WAPDA for this. I guess they should have chosen better partners than JJV.
@NA: Not quite !!!
@hedgefunder: Just a frustrated Indian...
@NA: That's the Problem with Pakistani Sense, rather than basic common sense.
we will process that dust and make some usable product
In fact all the employees of power plant are getting salaries till today when the plant is closed since 2006...
Alas Pakistan!!
shameful act or shameless act,,,i cant decide. I love this proud nation.
Why? Yet the country has coal reserves to the tune of perhaps millions of tons !!! Why? In time of such pathetic situation with power cuts that even the industries suffer? Who is responsible for this in reality? The answer is simple, the people of Pakistan, as you choose your rulers, knowing full well their past track record and their backgrounds too ! Why?
How does a union benefit by putting a plant out of business? If he country is in such desperate need for energy why doesn't the govt or SC put this higher on it's list of things to fix - rehabilitating existing plants seems like an inexpensive and quick way to help with the shortage.