Discussing the matter of delay in release of funds, Secretary Communications Jawwad Rafique Malik informed the meeting that the Ministry of Communications including National Highway Authority (NHA) had received no funds under the PSDP during the last six months.
Addressing the meeting, chaired by Senator Agha Shahzaib Durrani, Planning Secretary Zafar Hassan clarified that the NHA received extra funds from foreign component; therefore the local component was adjusted in total allocation. He said there were two components of the funding, one was foreign and the other was local one.
“According to the rules, PSDP size must not exceed the allocation size whether the money is adjusted from outside or from within the country,” Hassan said, adding that the NHA received 134% of its allocation during the previous fiscal year.
“An amount of Rs251 billion was released for various development projects of NHA against the total allocation of Rs188 billion.”
He explained that the extra amount came from the Chinese side specifically for Multan-Sukkur and Havelian-Thahkot motorways, which was adjusted against the total allocation and funding from local component was stopped. The planning secretary added that Rs116 billion was allocated under local component for NHA projects, however, Rs76 billion were released during the year 2018-19.
Hassan said that during the ongoing first quarter of the current fiscal year, Rs19.2 billion were to be released in by September 30, and out of this amount, Rs13.5 billion was to be released for the approved projects while the rest was allocated for unapproved projects.
“Out of Rs13.5 billion for approved projects, the government has released Rs10.1 billion so far.”
On the other hand, communications secretary said that since the local allocation was made for a number of small projects, which had not been released due to the matter of adjustment, work on all these projects had been delayed and the contractors had refused to continue work on these projects for which no bills were generated for the last six months.
He asked the committee to recommend early release of funds for these projects to avoid any further delay in the projects.
Published in The Express Tribune, September 25th, 2019.
Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.
COMMENTS
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ