Expressing dismay over the failure of drainage system due to BRT project’s excavation, he directed the Peshawar Development Authority and Water and Sanitation Services Peshawar to get the sewerage system flowing within one-and-a-half month.
While hearing the water treatment plant case, PHC two-member bench comprising Justice Qaiser Rashid and Justice Muhammad Ghazanfar Khan had summoned the secretary local government. Justice Rashid asked the city’s managers why there were no water drainage lines in the project.
“We have seen that after few hours of rains the PDA employees are digging the sides of the BRT and pavements of roads to make way for the rainwater to flow out,” he said.
Published in The Express Tribune, April 18th, 2019.