LNG supply line to Lahore ready   

400 million cubic feet LNG gas has been included in the system for the industrial sector


APP December 28, 2016
PHOTO: EXPRESS

LAHORE: The 750-kilometre LNG supply line from Sukkur to Lahore has been completed while work on the remaining 250-kilometre will be completed in March 2017. This was stated by Sui Northern Gas Pipelines Limited General Manager Project Sibghatullah while talking to APP on Wednesday.

North-South pipeline: Pakistan, Russia reach LNG price accord

He said that the LNG-based power projects including Nandipur, Haveli Bahadur Shah, Baluki and Bhikki would be provided 1,200 million cubic feet gas. “An 18-kilometre-long supply line has been provided to Bhikki power project and the department will start giving gas on demand,” he added.

He said that 400 million cubic feet LNG gas has been included in the system at this time and is being provided to the industrial sector.

Published in The Express Tribune, December 29th, 2016.

Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.

COMMENTS

Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ