During his visit, the chairman observed that progress on most of the components was ahead of the revised schedule.
He appreciated project authorities, consultants and contractors for their efforts in expediting the construction work and directed them to continue working at the same pace to complete the strategically important project on time.
ECNEC says yes to Neelum-Jhelum, CPEC road projects
The chairman visited the dam site at Nauseri, river crossing at Majohi to attend the break-through ceremony of the right tunnel and power house at Chattar Klas.
It is pertinent to mention that the two sections of the right tunnel - one excavated from the dam site and the other from the power house - were connected on January 9 against the target date of January 15.
“The Neelum Jhelum project is a monument of the Pak-China friendship towards the development of hydropower in Pakistan,” said the chairman while performing the connecting ceremony of the two sections. He was also briefed that the overall progress of the project currently stood at 76%; out of the 68km long tunnel, so far 59km have been excavated while 74% of the dam construction is complete.
Hydroelectric power plant: Financiers stop $433m loan for Neelum-Jhelum project
The power house and the switchyard of the project are scheduled to be completed in November this year.
Upon completion, the Neelum Jhelum Hydropower Project will contribute 5.15 billion units of electricity every year to the national grid.
Published in The Express Tribune, January 22nd, 2016.
Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.
COMMENTS (1)
Comments are moderated and generally will be posted if they are on-topic and not abusive.
For more information, please see our Comments FAQ