27 trains to be acquired for metro project

The track will be equipped with telecom, radio, CCTV, a public address system and an audio-video recording system


Imran Adnan February 04, 2016
A dummy image of a metro train station as envisioned by the Punjab government. PHOTO: PR

LAHORE: As many as 27 trains will ply the Orange Line metro train (OLMT) track with an average headway of two minutes.

Documents available with The Express Tribune indicate that 27 train sets, comprising of 135 cars, would be procured at an estimated cost of $1 billion. The project will be funded through a loan provided by China’s Exim Bank. These trains will run on the Orange Line in five-car formation that will include three motor cars and two trailers.

'Metro train will be completed in 2 years'

The new mass transit system has the capacity to carry 30,000 passengers per hour. As many as 300,000 passengers are expected to use the train daily. Operating hours of the Orange Line metro train will be 18 hours (5:30AM to 23:30PM).

Maximum speed of the train has been set at 80 kilometres per hour, barring some turns and curves.

Documents show that a double-track will be built, with three rails on each track.

The middle rail at the bottom of each track will energise trains with 750-volt direct current. These trains will have a stainless steel, fireproof body.

Wires and cables used on the rolling stock shall be halogen-free, fire-retardant and low-smoke. No flammable material will be used in the rolling stock.

Civil society urged to support Metro train

Two high-voltage substations will be built near the University of Engineering and Technology (UET) and the Shahnoor Station. Each substation will be connected to 132KV power supply.

The project will also have a Power Supervisory Control and Data Acquisition System (PSCADA) for monitoring, control and communication. This system will enable provision of data and control of the power rail.

Transport: ‘Revise Metro train project’s model’

The OLMT track will be equipped with telecom, radio, CCTV, a public address system and an audio-and-video recording system. The orange line will also have an automatic train control (ATC) and a modern signalling system.

In summer, public areas of the OLMT stations will have air conditioning facility with mechanical ventilation in other seasons. Fire detection, automatic and semi-automatic ticket selling and checking systems are also part of the design.

Published in The Express Tribune, February 5th, 2016.

COMMENTS (19)

Rahul | 8 years ago | Reply @SHAH: The Dhaula Kuan airport express station has that. Glass partitioning with electric doors synced with the metro. He's probably referring to that.
Rahul | 8 years ago | Reply @Malik Saab: I don't need to be a Pakistani to comment on Pakistan. Just like you don't need to be an Indian or an Afghan to meddle in their internal affairs. This is the internet. You can comment where ever you want.
VIEW MORE COMMENTS
Replying to X

Comments are moderated and generally will be posted if they are on-topic and not abusive.

For more information, please see our Comments FAQ